Increasing security of electricity supplies for both the UK and France.

Onshore cables

  1. The HVAC and HVDC cables related to the converter station will make landfall at Monk’s Hill beach.
  2. We will lay HVDC and HVAC cables to and from the converter station along one of the runways at Solent Airport. We’ll start this work in October 2018 and finish in October 2019.
  3. The HVAC cables will run along the bottom of the Solent to Chilling. We’ll lay these in 2019.
  4. The HVAC cables will make landfall at Chilling.
  5. We will lay HVAC cables between the landfall and connection point at Chilling. We’re carrying out construction work here until September 2018, and then installing the cables in 2019.
  6. The HVAC cables will connect to the national electricity transmission system at a substation in Chilling.

Airfield

Our HVAC and HVDC cables will connect to the Converter Station, the route from Monks Hill Beach to the Converter Station involves the installation of the cables onto Solent Airport.

Work on the airfield during 2018 and early 2019 involved excavation of trenches and joint bays, installation of ducts for the cables in the trenches, backfilling and reinstatement. Installation of the cables and jointing works will follow on from this work during spring and summer of 2019.

In October 2017, National Grid IFA2 undertook EMF trials on Solent airport. Using AC and DC cable systems installed and energised in the configuration and current rating reflecting the actual conditions in service. This was to verify compliance with the planning conditions and that there was no interference with aircraft avionics.

All participants, including airfield users confirmed that:

  • During the trials all aircraft systems functioned as normal
  • There were no anomalies observed on any of the aircraft avionics
  • Magnetic compass deviation was temporary and minor
  • For more information on Solent Airport please visit www.solentairport.co.uk

What are we doing in the next three months?

  • We have finished laying the offshore HVAC cables and are now burying them. 
  • To prepare for the arrival of the HVDC cables we are digging a trench in the intertidal area at Monks Hill Beach.

Monks Hill Beach

This is where both the HVAC and HVDC cables will come onshore. All work will take place within a compound in the eastern part of the car park. We’ll access this using a purpose-built haul road through a field to the north of the car park. This will mean full public access to the western part of the car park; the beach and the beach huts are preserved throughout the construction period.

Our work will consist of the excavation of trenches to install the cable ducts, backfilling and reinstatement and the construction of 3 transition joint bays in the car park which will be backfilled and reinstated after completion of the jointing works.

When carrying out this work we will:

  • Ensure the working areas are safely segregated from the public
  • Complete the beach works and work within the eastern car park area within one season (2019)
  • Maintain access to the western section of the car park ensuring that access to all beach huts is maintained.

Monks Hill Beach information poster

 

What are we doing in the next three months?

  • Fencing is in place on the beach and pink buoys are positioned on the water around our jack up barges, the C57 Red Squirrel and C59 Emotion, to mark our working construction area. There are open excavations and obstructions under the water and the area is therefore restricted for your safety. Please do not enter this restricted working area on the beach or in the water. For more information please see the poster above. These vessels are expected to depart in WC 9/9/19.
  • The CAPALL MARA (shown below) will arrive on site shortly for trenching work associated with the HVDC cables. We will be working up to 2km from shore with the CAPALL MARA and will share further details shortly. The HVDC cable pull is scheduled for mid-October after CAPALL MARA has completed trenching works.
  • We have site hoardings around the area to the south of Crofton Avenue which is the main access for our construction traffic down to Monks Hill Car Park.
  • We have completed the installation of sheet piling off Monks Hill Beach. We aim to finish trenching work there by mid-September and will then return the beach to its original condition.
  • We have temporarily diverted the public footpath from the car park to The Shack café while we excavate trenches underneath the footpath route. The temporary footbridge in place as part of the diversion will be removed in WC 9/9/19.
  • We are burying the six HVAC cables between Monk’s Hill Beach and Chilling using the JIF ARTEMIS and GREEN QUEST (safety vessel). We expect to complete this work in November.
  • The current position of our vessels can be tracked on the MarineTraffic.comtool on the Offshore Cable section of this site.

C57 Red Squirrel

The CAPALL MARA

Chilling

Chilling is the point that IFA2 will connect to the electricity transmission network. We are laying cables from the shore area to an existing National Grid facility on Chilling Lane.

We have used a technique known as Horizontal Direct Drilling (HDD) to install cables in the shore area. This involves drilling underground and installing a series of ducts, which we then pull the cables through.

Elsewhere, we will dig trenches, bury the ducts, reinstate the ground, and pull the cables through. In all cases, the cables will not be visible when we have finished. For further information on NGET and the work at Chilling please visit: https://www.nationalgridet.com/infrastructure-projects/ifa-2-connection 

Programme

To reduce the impact of our project traffic in the area we will do the following:

  • Impose a 10mph speed limit for construction vehicles through Hook Village
  • Escort any HGVs moving through Hook Village
  • Brief drivers about Chilling Lane’s use as a footpath and cycleway

What are we doing in the next three months?

  • We have now completed the crossings over Chilling Lane and Workmans Lane.
  • We returned to site in mid-March after a shutdown period to protect overwintering birds.

Last updated: Wednesday, September 4, 2019


Our fossil heritage revealed

See more »

News

  • Monday, January 1, 2018

    Information events about the final plans for IFA2

    In November 2017, Fareham Borough Council granted National Grid full planning permission for the project and agreed to lease land at Solent Airport, Daedalus to build a converter station. Following this decision we plan to start construction work in January / February 2018.

    In November 2017, Fareham Borough Council granted National Grid full planning permission for the project and agreed to lease land at Solent Airport, Daedalus to build a converter station. Following this decision we plan to start construction work in January / February 2018.

    We would like to give local residents the opportunity to hear about the next stage of the IFA2 project and answer any questions that you may have. You can find out more at our information event, which will take place on 31st January 2018 between 4:30pm and 8:30pm at CEMAST College, 1 Meteor Way, Broom Way, Fareham, Lee-on-the-Solent PO13 9F.

    We hope to see you at the events. If you have any questions in the meantime, please contact us on 0800 0194 576 or info@ifa2interconnector.com

    Read more »