Increasing security of electricity supplies for both the UK and France.

Onshore cables

  1. The HVAC and HVDC cables related to the converter station will make landfall at Monk’s Hill beach.
  2. We will lay HVDC and HVAC cables to and from the converter station along one of the runways at Solent Airport. We’ll start this work in October 2018 and finish in October 2019.
  3. The HVAC cables will run along the bottom of the Solent to Chilling. We’ll lay these in 2019.
  4. The HVAC cables will make landfall at Chilling.
  5. We will lay HVAC cables between the landfall and connection point at Chilling. We’re carrying out construction work here until September 2018, and then installing the cables in 2019.
  6. The HVAC cables will connect to the national electricity transmission system at a substation in Chilling.

Airfield

Our HVAC and HVDC cables will connect to the Converter Station, the route from Monks Hill Beach to the Converter Station involves the installation of the cables onto Solent Airport.

Work on the airfield during 2018 and early 2019 will involve excavation of trenches and joint bays, installation of ducts for the cables in the trenches, backfilling and reinstatement. Installation of the cables and jointing works will follow on from this work during spring and summer of 2019.

In October 2017, National Grid IFA2 undertook EMF trials on Solent airport. Using AC and DC cable systems installed and energised in the configuration and current rating reflecting the actual conditions in service. This was to verify compliance with the planning conditions and that there was no interference with aircraft avionics.

All participants, including airfield users confirmed that:

  • During the trials all aircraft systems functioned as normal
  • There were no anomalies observed on any of the aircraft avionics
  • Magnetic compass deviation was temporary and minor
  • For more information on Solent Airport please visit www.solentairport.co.uk

What are we doing in the next three months?

  • We are currently installing ducts above Monk’s Hill beach and are welding pipe sections which will carry the cables in the cable ducts.

Monks Hill Beach

This is where both the HVAC and HVDC cables will come onshore. All work will take place within a compound in the eastern part of the car park. We’ll access this using a purpose-built haul road through a field to the north of the car park. This will mean full public access to the western part of the car park; the beach and the beach huts are preserved throughout the construction period.

Our work will consist of the excavation of trenches to install the cable ducts, backfilling and reinstatement and the construction of 3 transition joint bays in the car park which will be backfilled and reinstated after completion of the jointing works.

When carrying out this work we will:

  • Ensure the working areas are safely segregated from the public
  • Complete the beach works and work within the eastern car park area within one season (2019)
  • Maintain access to the western section of the car park ensuring that access to all beach huts is maintained.

The NP 289

C57 Red Squirrel

Monks Hill Beach information poster

HVAC vessel work areas

What are we doing in the next three months?

  • We have established site hoardings and a stoning the area to the south of Crofton Avenue which is the main access for our construction traffic down to Monks Hill Car Park.
  • Fencing is being put up on the beach in front of these hoardings for approximately two months. Access along the car park from East to West, and to The Shack, will be maintained. This fencing marks our working area for excavating trenches for the interconnector cables. Pink buoys will mark our working area on the water. There will be open excavations and obstructions under the water and the area is therefore restricted for your safety. Please do not enter this restricted working area on the beach or in the water. For more information please see the poster above.
  • Excavation work for cable duct trenches is under way behind our hoardings at Monks Hill Car Park and will start on the beach late April.
  • Our jack up barge, the C57 Red Squirrel, will be arriving from Southampton and will be visible from the beach as it carries out work in the water off Monk’s Hill car park. The working area for this barge is marked by buoys and will be patrolled by safety vessels for your protection; please avoid this active working area. This is accompanied by another barge, the C59 Emotion.
  • The NP 289, our cable laying barge will be moving between Monk’s Hill Beach and Chilling to lay the six HVAC cables from late June for approximately two months. The vessel’s working and anchor areas will be marked by buoys to create a safety zone for your protection. The barge moves on anchors; its route and the anchor point areas are shown in the chart above. Please be vigilant on the water and avoid this working area.
  • The current position of our vessels can be tracked on the MarineTraffic.com tool on the Offshore Cable section of this site.

Chilling

Chilling is the point that IFA2 will connect to the electricity transmission network. We are laying cables from the shore area to an existing National Grid facility on Chilling Lane.

We have used a technique known as Horizontal Direct Drilling (HDD) to install cables in the shore area. This involves drilling underground and installing a series of ducts, which we then pull the cables through.

Elsewhere, we will dig trenches, bury the ducts, reinstate the ground, and pull the cables through. In all cases, the cables will not be visible when we have finished. For further information on NGET and the work at Chilling please visit: https://www.nationalgridet.com/infrastructure-projects/ifa-2-connection 

Programme

To reduce the impact of our project traffic in the area we will do the following:

  • Impose a 10mph speed limit for construction vehicles through Hook Village
  • Escort any HGVs moving through Hook Village
  • Brief drivers about Chilling Lane’s use as a footpath and cycleway

What are we doing in the next three months?

  • We have now completed the crossings over Chilling Lane and Workmans Lane.
  • We returned to site in mid-March after a shutdown period to protect overwintering birds.

Last updated: Thursday, May 2, 2019

Update on Broom Way construction work

See more »

News

  • Thursday, March 15, 2018

    Tree planting marks the start of open space for IFA2

    National Grid IFA2 Ltd marks the beginning of the creation of the public open space with a ceremonial tree planting event.

    National Grid IFA2 recently commenced the beginning of construction at the IFA2 site by inviting Fareham Borough Council leader, Cllr Sean Woodward, and other community representatives to mark progress and take part in a ceremonial tree planting event. 

    In partnership with Fareham Borough Council, it is anticipated that over 30,000 native trees both new and mature, will be planted to create an enhanced habitat across the space and appropriate screening to the north and east of the converter station. This is the start of National Grid IFA2 providing 38 acres of public open space as part of its commitment to the local community. 

    IFA2, which received planning permission last year, will be a high voltage direct current (HVDC) electrical interconnector linking the British and French transmission systems. Once operational, IFA2 will be capable of exporting or importing 1000MW of power between the two countries, enough to power around 1 million homes. 

    David Luetchford, Head of National Grid IFA2 said: “It was great to welcome Cllr Woodward and other local representatives to the IFA2 site yesterday to mark the start of construction. We are making a major commitment to the local community: we’ll deliver over 38 acres of open space for local people to enjoy, and we’ve signed up local companies to support this work. We look forward to working closely with the Council over the next two years to create this new resource for the community.” 

    Leader of Fareham Borough Council, Cllr Sean Woodward added: “It was an honour to plant the first tree here. The Council has always been keen for a large area of public open space to accompany construction of the Interconnector, so it’s great to see this coming to fruition and I look forward to it being open for residents to enjoy.”  

    Read more »
  • Monday, January 1, 2018

    Information events about the final plans for IFA2

    In November 2017, Fareham Borough Council granted National Grid full planning permission for the project and agreed to lease land at Solent Airport, Daedalus to build a converter station. Following this decision we plan to start construction work in January / February 2018.

    In November 2017, Fareham Borough Council granted National Grid full planning permission for the project and agreed to lease land at Solent Airport, Daedalus to build a converter station. Following this decision we plan to start construction work in January / February 2018.

    We would like to give local residents the opportunity to hear about the next stage of the IFA2 project and answer any questions that you may have. You can find out more at our information event, which will take place on 31st January 2018 between 4:30pm and 8:30pm at CEMAST College, 1 Meteor Way, Broom Way, Fareham, Lee-on-the-Solent PO13 9F.

    We hope to see you at the events. If you have any questions in the meantime, please contact us on 0800 0194 576 or info@ifa2interconnector.com

    Read more »