Increasing security of electricity supplies for both the UK and France.

HVAC Cable

IFA2 is in the process of installing six HVAC cables between Monk's Hill Beach and Chilling. This work has been progressing well, we have now laid all of the cables.

We will now bury the HVAC cables and continue to prepare for the arrival of the HVDC cables from France.

What are we doing in the next three months?

  • Our HVAC burial vessel JIF ARTEMIS is burying the HVAC cables beneath the seabed. We expect this work to last until November.
  • Our support vessel, GREEN QUEST, will be in the area assisting JIF ARTEMIS.
  • Please be extra vigilant in this construction area during the installation period. We are very grateful for your patience and cooperation.

JIF ARTEMIS

GREEN QUEST

The current position of our HVAC vessels can be tracked using the MarineTraffic.com tool below.

HVDC Cable

The HVDC cables linking the electricity transmission systems of Great Britain and France are an essential part of IFA2. We will carry out the work to lay these cables in 2019.

The cables will be buried in the seabed. We’ll install the cables using large specialist vessels which are able to transport and lay long sections of cables (up to 100 km). Some cable joints will need to be made at sea during the installation process.

The current position of the HVDC cable laying vessel, the Cable Enterprise, can be tracked using the MarineTraffic.com tool below.


Cable Enterprise

What will happen in the next three months?

  • The CAPALL MARA (shown below) is currently completing trenching works up to 2km from shore. Works will continue throughout November to return the area back to normal and make it safe for water users.
  • The final HVDC cable pull-in at Lee on Solent has been completed and The Cable Enterprise is now laying cable through the Solent. This work will be completed by the end of November.

The CAPALL MARA


The above chart shows the position that we are at in the HVDC cable lay process. We are currently at point KP165.

Last updated: Friday, November 15, 2019


National Grid IFA2 and the Fairey Barracuda story: additional date now available!

See more »

News

  • Saturday, September 1, 2018

    Boulder removal work update

    We have been carrying out debris route clearance, archaeological target investigations and boulder removal work along the HVAC route. This activity was completed in November 2018.

    We have been carrying out debris route clearance, archaeological target investigations and boulder removal work along the HVAC route.

    This activity was completed in November 2018.

     

    Read more »
  • Wednesday, August 1, 2018

    Broom Way construction

    We wrote to residents of the Lee-on-the-Solent area on 29 May 2018 to inform them that we anticipated closing one lane of Broom Way to traffic for five days from 11 June 2018 while we created a new access to the converter station site. We are now no longer planning to carry out this work in this period. This will now be rescheduled to a future date. We are grateful to members of the community for bearing with us, and will provide an update on the rescheduled work in due course.

    We wrote to residents of the Lee-on-the-Solent area on 29 May 2018 to inform them that we anticipated closing one lane of Broom Way to traffic for five days from 11 June 2018 while we created a new access to the converter station site.

    We are now no longer planning to carry out this work in this period. This will now be rescheduled to a future date.

    We are grateful to members of the community for bearing with us, and will provide an update on the rescheduled work in due course.

    Read more »
  • Thursday, March 15, 2018

    Tree planting marks the start of open space for IFA2

    National Grid IFA2 Ltd marks the beginning of the creation of the public open space with a ceremonial tree planting event.

    National Grid IFA2 recently commenced the beginning of construction at the IFA2 site by inviting Fareham Borough Council leader, Cllr Sean Woodward, and other community representatives to mark progress and take part in a ceremonial tree planting event. 

    In partnership with Fareham Borough Council, it is anticipated that over 30,000 native trees both new and mature, will be planted to create an enhanced habitat across the space and appropriate screening to the north and east of the converter station. This is the start of National Grid IFA2 providing 38 acres of public open space as part of its commitment to the local community. 

    IFA2, which received planning permission last year, will be a high voltage direct current (HVDC) electrical interconnector linking the British and French transmission systems. Once operational, IFA2 will be capable of exporting or importing 1000MW of power between the two countries, enough to power around 1 million homes. 

    David Luetchford, Head of National Grid IFA2 said: “It was great to welcome Cllr Woodward and other local representatives to the IFA2 site yesterday to mark the start of construction. We are making a major commitment to the local community: we’ll deliver over 38 acres of open space for local people to enjoy, and we’ve signed up local companies to support this work. We look forward to working closely with the Council over the next two years to create this new resource for the community.” 

    Leader of Fareham Borough Council, Cllr Sean Woodward added: “It was an honour to plant the first tree here. The Council has always been keen for a large area of public open space to accompany construction of the Interconnector, so it’s great to see this coming to fruition and I look forward to it being open for residents to enjoy.”  

    Read more »